2025 Street Reconstruction Project and Utility Extension (Colonial Woods and Pine Haven)

Project includes the following roadways:

  • Colonial Woods (Red Maple Lane and the easterly portion of 62nd Street)
  • Pine Haven (81st Street, Danube Street, Elbe Street)
  • Evergreen Trail and Diane Street as overlays

View map.

On February 24, 2025, the City Council called for an Assessment Hearing for extending sewer and water in the Colonial Woods and Pine Haven neighborhoods. This hearing happened on March 24, 2025, and notices were mailed to each property owner.

Construction began in April of 2025 and will continue through the fall of 2025. Final restoration will be completed in the spring of 2026.


Lake Drive closure

The contractor will close Lake Drive on Monday, April 28. The road will be closed to all traffic from 300 feet north of Main Street to Diane Street for approximately four to five weeks. The intersections of Lake Drive with Main Street and Diane Street will remain open, but the intersection of Lake Drive and 81st Street will be closed. Residents of the Pine Haven neighborhood will need to use the access off Main Street to get in and out of the neighborhood during this time.

Please follow detour signs routing traffic to I-35 and I-35W. Detours must be on roads that can handle the additional traffic, so it is important to use the detour route.  


Map of a road detour on Lake Drive

September 29th Update:

This will be the last weekly update as the project is anticipated be substantially completed this upcoming week. The City will be working with the contractor on final clean up items and completing the final layer of pavement through the spring of 2026. Thank you for your patience with construction this year.

Colonial Woods Neighborhood (Red Maple Lane and the easterly portion of 62nd Street)

  • Sod/seed installation is anticipated to begin next week.
  • Mailboxes are anticipated to be installed on Monday, September 29th.
  • The City anticipates issuing service connection permits next week.  Sewer and water connection permit applications can be found on the City’s website.

Pine Haven Neighborhood (81st Street, Danube Street, Elbe Street)

  • Project is substantially complete.
  • The City anticipates issuing service connection permits next week.  Sewer and water connection permit applications can be found on the City’s website. 

Evergreen Tr and Diane St

  • Project is complete.